What a relief it is to see that fascia board over the dormer windows stained! Its significance is added to by the knowledge that all of the eaves and their pesky little cubbies between rafters were stained in the same afternoon. Egad! Three cheers for the staining crew, of which C and I provided the grand finale (we thought -- more about that in a minute). To the left in this photograph may be seen the still as yet unsided bow wall, prepped (with shims over the studs) in order to receive the cedar siding boards, which were planned to run the full width and height of the wall. However, after much (much!) discussion, it was decided to put up a sort of pentagon of cedar 1x3s, about a foot in from the outside edges of the wall and eaves, and side around that, leaving the inside of the pentagon to be paneled with stained luan. This would finish the bow wall more quickly, and leave it weatherproof (enough) to survive until the shed, which could be constructed separately and installed finished (like a kitchen cabinet -- thanks Big D!) would be installed.

To that end, Kyle removed all the carefully attached shims. As the bow wall now needed a new pattern of them, he made several more, and attached them in their new pattern.
Around this time, we had a day or two of chilly windy weather, reminding us that the idyllic days of Indian summer were not going to last forever. In the studio it was more protected from the breeze, but not too much warmer than outside.
Mid-shim-making, with luan and other bits of lumber leaning against the port wall. The wheels are covered here with an old vinyl tablecloth, a test of something I had been meaning to do ever since I noticed that the afternoon sun had been beating down unmercifully on those rubber tires all summer long. The wind blew it half off in a day or two. Clearly I need to do more than tuck it snugly around the tires.
Two sheets of 5/16" luan plywood, stained face and edges, waiting to dry and be cut to go up on the bow wall. This was the extra staining that came up suddenly. Kyle got the luan, and needed to cut it (stained) the same day in an effort to get the bow wall done before the party. I gave the two sheets and their edges a good thick coat, along with the hopes the luan would survive winter exposure.
Stage one of the bow wall siding turned out to be attaching the pentagon of luan, including a drip edge along the horizontal seam, and flashing along the top diagonal edges of the paneling. Next, stained cedar 1x3s would be screwed on top of the paneling, to secure the luan (which doesn't line up perfectly with the studs inside) as best we could. In part, the paneling will be attached only to the 3/8" plywood sheathing.

This was the moment when the saving of all those short pieces of cedar siding came in handy. It was very satisfying to be able to get all the bow wall siding done using the "leftover" pieces, and Kyle said it was almost uncanny how perfectly it worked out. We had realized several weeks before that if we were going to completely cover the bow wall with cedar siding boards, we would have to order more. And shell out more money. And stain more. Hence this change of design was helpful on many fronts, and resulted in the bow wall looking gorgeous in time for the long-awaited tiny house-warming party!
Voila!
This close-up photograph shows both drip edge and flashing, making the wall complete and weatherproof for the time being, and still ready to have a shed slipped in and hung like a cabinet later.
And, after many weeks of dry weather, a full day of rain came along, and thankfully the drops beaded up beautifully on the siding, trim boards and stained luan. Yay!
It has become obvious to me that I have entered a new era in the
housebuilding process. With the exterior construction more or less
nearing completion, and various next steps awaiting attention, a lot of
juggling and some serious prioritizing has become the norm. All of a
sudden there seem to be a million details all at the top of the list:
wiring and electrical fixtures and devices, both 120V and 12V, heating
system decisions, wall coverings, fastener types, vent fans (solar, 120V
and 12V!), trailer lighting fixture replacement, shed design and
hardware decisions, loft ladder construction, floor sealing, et cetera,
et cetera.

Additionally I have of course been getting antsy to install interior cupboards, the windowseat/bed unit, and re-purpose and up-cycle many of my collected possessions into useful parts of my tiny house. Most of these re-construction projects first involve heavy lifting somehow, so I am stymied immediately on initiating these thrilling projects. But, lo and behold, thankfully a friend actually expressed interest in the futon mattress that had been on this frame for years, as my couch. So I rolled it up and tied it into a big slug-like floppy roll. And she and her son came over a few days later and took it away!! The next step is to disassemble the frame and get it moved to the tiny house so I can start modifying it into the folding windowseat bed.

Another topic which naturally deserves top priority attention too is the acquisition (or not?) of a tow vehicle. B's Suburban turns out to have a tow bar mounted on the frame and not the bumper (who knew?) and thereby is capable of towing more than was mentioned in the specs I glanced at after I first saw it. It could easily tow my house! That certainly caught my attention. A Suburban would probably be a great choice as it is like a station wagon version of a truck. My budget cannot handle the purchase (or probably insuring) a new vehicle, so I am keeping one eye open for likely prospects, keeping in mind that what I want is an old (i.e. inexpensive) but faithful (i.e. reliable for a few years) truck/vehicle capable of towing 10,000 lbs. I have learned in the course of my ingenuous conversation with a number of folks, with whom I probably would otherwise not have had anything to talk about, that I want a 3/4 ton pickup, with a heavy towing package. This includes a special radiator. Also a trailer brake set-up, so as to have the trailer brakes do their duty of slowing the trailer at the same time as, or just a little ahead of, the truck. Do I want diesel? Or do I not want diesel? Or do I just want to hire people who own such trucks to tow the house anytime I move it? Research is ongoing behind the scenes. But as with every aspect of this process, there is a lot of advice available, in person and online, some of it conflicting, but no way to know exactly when I have done enough research and can make a choice. That is the bad news, and the good news -- there is so much to learn!

For a temporary entry door, I bought an inexpensive interior hollow core door, coated one side of it with three coats of exterior latex paint. Then I got the brilliant idea of making it a Dutch door! I marked it, had it cut in two, and pulled out the cardboard supports, replacing them with XPS rigid foam insulation and a reflective layer of bubblewrap insulation. It is going to be a good test to see if a Dutch door is right for me, before we start messing with the circa 1782 door from the house I grew up in. I clearly remember loving the Dutch door on my childhood playhouse, but am willing to entertain the possibility that my tastes have changed in the last 50 years. I will find out! However if this door gets me through the winter and a trip to my dear friend in B-----, MA., that will suffice. I have my doubts about it lasting through too many wet rainy days, but will report.
A view of the house at night, as construction lights on two long extension cords from Big D's studio give it a homey feeling when seen from the outside.
Okay, here is the news you've been waiting for! M, having completed the hammered copper shower pan, spreads some M-1 adhesive (from the steel company where we got the copper and the roofing material), preparatory to inserting the pan into the sturdy wooden frame.
And...it is in!! M has piled various anvils and bags of concrete into the pan to make an excellent seal, and clamped everything that could be clamped. Then she waited, a day, two days, perhaps even three -- and...
Oops! This is actually a photo of the shower pan before it was adhered to the frame! Drat! Well it looked just like this from this angle after it was attached.
The scene shifts to evening in the tiny house, as Kyle and M install the shower pan. Kyle drilled a 3" hole, through the floor, the insulation layer, and the steel trailer bottom for a drain pipe that will gather grey water into a holding tank and discharge system.
They test the drain, and decide that gasket under the brass fitting is too stiff and too thick, and therefore interferes with the seal, allowing water to sneak between the gasket and the copper. Replacement with a squishier, thinner gasket is pending.
The shower pan is, however, installed! And insulation in the empty bays (with XPS, not polyiso) and walling the shower stall with Wedi material can proceed. Under the curb of the entry corner of the shower may be seen a gap. This is to allow access to the washer/nut which must be loosened if ever the shower pan would be removed. It will also be a bit of storage space under the shower stall, perhaps for the wrench that would be needed to loosen the washer/nut!
This photograph has a warmer tone to it, and the copper looks more as it really does. It is a beautiful piece of art work, a sculpture really. And it will be a joy to have in my line of sight. It will surely assist me in tasks of everyday living, such as washing clothes and dishes, and rinsing paintbrushes and clay tools out, in addition to being a simple shower. Thank you!
After many (many!) brainstorming sessions to come up with something to use as a wallcovering instead of drywall, which is way too heavy, I finally settled on this thin luan plywood. Not particularly environmentally correct in any way, the choice of luan came down to weight, expense, and ease of installation. This is a thickness usually used for underlayment, and it has considerable flexibility, and I only hope that it doesn't droop or sag too soon. I plan to do a sort of board and batten look eventually, covering the seams and lines of nails with strips pf lath, and, when painted, I hope it will look simple and clean, not cheap and crappy....
Kyle and B set up a cutting station right outside the house, since no rain was forecast, and after that the installation went very quickly.
Here they are putting up the loft ceiling sheets. It was handy for them to work as a duo at this point, although either of them could have managed it alone. Using a lot of measurement, and a lot of compressor nail gun work, they fastened the luan up with 3/4" finishing nails or tacks. The ceiling was up in an afternoon that stretched to sunset.
To B's right may be seen wallcovering on the loft dormer cheek walls. It was grand seeing that fiberglass-covered polyiso getting covered up so quickly. No moisture barrier was used on the ceiling, but plastic sheeting was installed on the walls as the work moved down to the first floor.
Work continued until dark and beyond some days, and the weather was very benign, giving us day after day of delicious Indian summer.
Enter M, a recent sculpture and new media graduate, whose name was given to me by the department technician, and who brought cheerful steadiness to his labor. He was very amiable about getting pulled into the time-crunch of the last week before the housewarming party. We wanted to get as much completed as we could, since a week after the party the house would be towed to a new location. Both Big D and B were incredibly gracious and generous about allowing the use of their equipment, and putting a well-deserved trust in Kyle's good treatment of it.
When the time came to start cutting holes in the luan for electrical boxes, I got an electric roto-zip tool, having used one on drywall in the past (as assistant instructor for a woman's home repair class program). It was a good tool to have even if it did have a mind of its own at times. Kyle's proficiency increased as he and the tool came to a better understanding.
This view shows the aft wall, which was covered entirely with luan, since the windowseat will be built in and would cover any wainscoting. On the far right in the photograph may be seen the unfinished area below the future chair rail; this will be covered with tongue and groove pine wainscoting or bead board.

Looking forward up into the loft, it may be seen that almost all paneling is in. Kyle spent some careful time working around the windows, so as to use as few small pieces of paneling as possible; he cut out rectangular holes from large pieces for the window openings. The unfinished triangular area in the bow wall will have two small triangles covering the insulation, and eventually in the center two openings will be cut out, to allow access to the upper part of the shed from inside. On the outside of the house, this area of the shed will be difficult to reach anyway, and it will be handy to have a cubby up in the loft. A final note on the luan: obviously it looks different in different lights, and often looks rather pink. I plan on painting it, or at least staining it, to tone down the pink, even though the actual grain pattern is very pleasing.
On the first day of installation of the polyisocyanurate rigid foam insulation, we were all reminding each other to make sure the roof membrane in the peak of the ceiling got sliced out (before the foam was installed!); otherwise all the meticulous attention to detail on Kyle's part for the roof venting system would be wasted. This was successfully accomplished in the loft peak, where the ridge cap had already been installed. Ultimately Kyle sliced out the portion in the peak of the great room from up on the roof, as he was installing that final ridge cap. This is B's helper, B, working up in the loft.

Here the polyiso blocks are being installed in the ceiling of the great room, the "cathedral ceiling". It turned out that no adhesive was needed, because B&B were able to cut the foam precisely enough that it could be friction-fit really securely. The two worst parts of the job were 1) the tiny fiberglass fibers which were mostly quite loosely attached to the dark facing paper, and brushed off easily onto clothing or skin ("the gift that keeps on giving," as B said), and 2) the peskiness of insulating around the electric boxes and wiring with spray foam, which comes in various expansion strengths (confusingly labeled), just to keep us guessing when we went to pick up supplies. Generally we wanted the spray foam with the smallest expansion rate, so as to more easily control the application around the wiring.

So the first day a lot was accomplished, by avoiding the spaces which had electrical boxes in them. The Xs below the level of the future chair rail in this view are reminders not to insulate before the installation of the shower pan, due to the carpentry installation process. The oil-filled electric radiator in the foreground was needed on a few unseasonably cold and gusty days, and was powered by an extension cord (two actually) from inside Big D's basement studio.
Then came the little chunks to be pushed into the spaces between to joists of both loft spaces; then triangles and other geometrical configurations, here seen in the bow wall of the sleeping loft.

Lastly on the insulation (except for the shower pan wall spaces), B and M (a new helper, a recent college graduate in sculpture and new media), and ultimately Kyle, had the fun of spraying foam into crevices and around electrical boxes. Some of the foam tended to get a little out of control, which necessitated shaving it off. Or in some cases the spray foam began lifting out the block of polyiso, which later necessitated shaving that off. The loan of an awesome flexible Japanese hand saw by B (who generously loaned a number of pieces of equipment and tools -- thanks so much!) made the insulation shaving go much more smoothly than it otherwise would have. So other than tossing more fiberglass fibers into the air and into cracks and all over the floor (fiberglass makes Laurie cranky, can you tell?) the insulation installation was a huge success!
The source of some crankiness, in the interest of having a really toasty home in cold weather...
Somewhat tidier but not yet fiber-free!! Where is the shop-vac? This post has a cliff-hanger ending....!!!
Kyle and electrician P converse about the construction portion of the installation of two exterior outlets on the house. One will be at the stern, looking ahead to a possible use on a porch, and the other is for the entryway light just outside the door, on the starboard side. It was decided to wire the entryway light connection as an outlet, and not hard wire the fixture. It was thought prudent to plan to remove the light fixture before barreling down the highway (creating 60 mph hurricane force winds) without having to worry about it being sheared off by the force of the wind. (Note Kyle's nifty styrofoam pads on the extension ladder in the background -- added in order to rest the ladder against the roofing without any nicks or scrapes or dings.
Here Kyle is installing the wiring box by the door, having custom-made a nifty reversed cedar siding frame for it that will hold the screws for the receptacle and lid.
And this is what the stern outlet looks like on the inside of the house, blocking having been added to secure the position of the box. It is the blue box you can see behind the short 2x4. The grey box is for an interior receptacle below the window seat. Eventually this small area will be filled with spray foam.
The finished stern exterior outlet with its cover, a nice bronze instead of the usual white or grey.
P rigged an instant roller for the 12V wire, with Big D's crowbar, Kyle's ladder, and a coat hanger from my trunk. It works perfectly. She gets the two lengths of 14-3 tinned copper stranded marine cable up in the peak of the ceiling in no time.
In mid-wire-pulling, I decide we need to re-route the 120V and the 12V cables to avoid the openings to the future cubby (the peak of the shed out on the tongue, which will be accessible from the loft, not the shed). What you see is the re-routed cables going down the starboard gable line of the bow wall. The cubby openings will be on either side of the two (tallest) center bays between the bow studs. P generously humored my change, and it was done by the end of the hour.
A piece of nifty scaffolding equipment of B's (shaped when folded up a bit like the letter "W") creates this gangway going from one loft to the other, allowing P to tie up the 12V cable with the 120V pipe and prepare the junction box for the chandelier fixture.
A view of the stern storage loft mid-wire-pulling. Note the 12V and 120V systems are two completely separate systems, and there is no inverter involved. The 12V will only be powered by the deep-cycle marine batteries and the 120V powered by household current from a friend's garage, or an RV hook-up.
Sketching for the positions of the marine 12V double receptacles. This is in the stern wall to starboard of the big window. The outlet will be accessible in the sidewall of the starboard bookcase in the windowseat nook. Probably for a USB charger!
We almost had enough 12V cable on the 100 ft. spool from the marine store, but ended up buying about 20 feet from a big box building supply store. It was stranded copper OS cable, 14-3, and worked fine.
Not to be forgotten at the tail end of the post is the taillight re-installation. Kyle removed these after the first towing journey for their protection during the heavy exterior construction phase. Now they will be replaced for good, ready for the next move!
Kyle is in the home stretch of the roofing installation here. The ridge cap goes on last, after cutting the roof wrap that was over the venting, and installing the perforated venting strip, and the Z trim. Lots of caulk and adhesive and rivets. All the screws are concealed. It turns out the dormer ridge cap line is lower than the main ridge cap line; the main (cathedral portion) ridge cap will be 2-3" higher than the dormer ridge cap. Though a little bit noticeable, all of it is entirely secure and weatherproof, and I am brainstorming a weather vane to be located there in the future. Perhaps made of the leftover copper from the shower pan!
Some of the tools of the concealed fastener standing seam metal roofing trade. Lots of delicate and gooey things to be worked with.
Here is a look at the dormer ridge cap (oops -- pictures in this post are not in chronological order!) during installation. Again, we have the higher geometry thing going here....
And, voila! The roof is finished! Looks awesome and lovely with the stained cedar siding. (Now if someone would only stain that ONE fascia board above the loft windows -- !)
Here is a look at the gable edge trim installed. Exquisite lines. I just want to HUG that roof!! (I can hear Kyle solemnly reminding me that every edge of metal is as sharp as a razor, and the metal is awfully easily bent...) And now on to the bow wall (soon), which has been on hold for quite a while as discussions take place about the design and construction of whatever manner of shed is being contemplated at the moment. There have been many.
Here is another interim shot of the floor. I haven't got a good picture of the finished combed stain. The polyisocyanurate rigid foam insulation installation began about two minutes after the floor was dry, and got covered with little shreds of foam in no time. A picture will be forthcoming when the polyurethane has gone on.
A gift from the garden on the hill, delivered by A, posed by me in the tiny house, as a hummingbird and a mole chatting around the stud. Delicious!
I took some shots of the loft windows to send to the screen-making shop in Loveland, so the proprietor could see where the little tabs were to go. To the left of the center latch is the tiny slot which I was noting.
It turns out that the little tabs were not used. The first of three screens, a test, was ready in a day, and fit perfectly. Holes will be drilled for the little metal posts to slip into, a sturdier method of securing them after all.
In the midst of the gathering momentum, I paused to make a sign for us to hold up at the airport for my friend C, returning from Australia. Her daughter E and granddaughter LL picked me up so we could meet the flight. What fun!